September 19, 2009
Ian Parsons and Nicole Pirko had the honour of hitting the first ball on the courts. |
 |
|
 |
|
|
|
|
The first official game was played by Dean Brown, Jamie Bentley, Taylor Fawcett, and Paul Deratnay. It was Ref'd by Fred Ried and marked by Terry Bruce. Nicole Pirko is the Pickering Recreation Complex Squash Professional |
 |
|
|
|
|
|
|
September 14, 2009
The courts are coming along and the word is that they will be ready for the Grand Opening on September 19th. The walls are up,floors are going in, the back walls are waiting to be installed. Looks like we will have doubles courts real soon now. |
 |
|
 |
|
|
|
|
June 21, 2009
The exterior of the addition is almost complete. only the stairwell to be finished. The ashfault and the sidewalk have been restored.
Now we wait to see what's inside. |
 |
|
|
|
|
|
|
May 24, 2009
The windows are all in and the surrounding area has been cleaned up. With the exception of the stairwell not many changes will be visible from the outside from now on. |
 |
|
|
|
|
|
|
April 7, 2009
The structure for the stairwell from the second level is now in place. |
 |
|
|
|
|
|
|
March 22, 2009
The structure for the stairwell from the second level is now in place. |
 |
|
|
|
|
|
|
March 13, 2009
Construction has blazed ahead in the last 12 days. The outer skin has been applied to the back wall of the courts.
|
 |
|
|
March 13, 2009 Cont'd
The walls on the arobics area are almost complete. The roof is on. Ducting and sprinkler systems are going in. |
 |
|
|
March 13, 2009 Cont'd
The wall to the hidden room has been opened. |
 |
|
|
March 13, 2009 Cont'd
Very soon the outside work will be completed and then the inside work will commence. |
 |
|
|
|
Click the picture for a larger view. |
|
|
March 1, 2009
Dispite the cold weather,construction has continued. The roof is on the court area. A plastic wind break is up to protect the workers as they install the outer facing of brick. |
 |
|
|
March 1, 2009 cont'd
On the arobics side of the construction, you can now see the window areas of the first floor and the door opening. The second floor walls are going up. |
 |
|
|
|
|
|
|
February 15, 2009
Some good weather days have made it possible to continue construction. The back wall is bricked. The workmen are working on the roof struts. |
 |
|
|
February 15, 2009 Cont'd
The framing of the arobics studios are complete. Work continues inside on the bottom level. |
 |
|
|
February 15, 2009 Cont'd
They have removed the cement siding from the tower. A hole has been ripped in the underlying structure to reveal the "hidden room". |
 |
|
|
|
Click the pictures to see enlarged version. |
|
|
January 25, 2009
The cold weather has taken its tole and slowed construction. Not much has been done over the last few weeks.. |
 |
|
|
|
|
|
|
January 12, 2009
The crane is lowering into place the ceiling beams on the arobics studio. Most of the beams are in place on the ceiling of the courts. |
 |
|
|
|
|
|
|
January 6, 2009
Construction on the doubles courts continued throughout the Holiday season and as you can see from the picture, the back wall is now up.
The ceiling gerders are in the parking lot so that I couldn't get as close a picture as I have in the past. |
 |
|
|
|
|
|
|
December 18, 2008
Construction on the doubles courts continues. The bleechers have been poured. You can see the stairs going up the middle. |
 |
|
|
|
|
|
|
December 10, 2008
Not much progress has been made this week. This is possibly due to the cold weather.
The bleechers have been poured. The second floor on the studios has been poured. |
 |
|
|
|
|
|
|
November 30, 2008
Work continues on the grandstand seating area.
The arobics area is enclosed with plastic tarps to aid working in that area. |
 |
|
|
|
|
|
|
November 23, 2008
The concrete for the bleechers has been poured. It is covered by plywood for protection as it cures.
The second floor on the arrobics studio is ready to be poured. |
 |
|
|
|
|
|
|
November 12, 2008
The cement pad was poured yesterday. Today they were cutting expansion slots in the pad. Scaffolding has been delivered to the site ready to be installed so that the second floor on the exercise area and the roof on the courts can be put in place.
|
|
|
|
|
Click the picture for an enlarged view. |
|
|
November 4, 2008
scafolding has been removed, the sand base for the cement floors has been leveled. The cement forming the bleechers has been poured. |
|
|
|
|
Click the picture for an enlarged view. |
|
|
|
|
|
|
October 26, 2008
Construction has been going for about a month. The base walls are up and a second layer of cinder blocks is being applied to right wall of the courts. |
|
|
|
|
Click the picture for an enlarged view. |
|
|